NEW QUESTION 29
What is created with subcontracting as a target and is assigned a subcontracting activity with the part to be provided and the corresponding material provision indicator?
- A. Virus
- B. Sandbox
- C. Maintenance order
- D. Heuristic
Answer: C
NEW QUESTION 30
What is the consequence when you activate alternative labelling?
Please choose the correct answer.
Response:
- A. You can change a primary functional location label and delete the old functional location label
- B. The labelling system must be assigned to the functional location category.
- C. You CANNOT deactivate an alternative labelling.
- D. You can change the primary functional location label and keep the old label as a historical label.
Answer: D
NEW QUESTION 31
Inspections and repair work requiring the shutdown of an entire asset is performed at regular intervals can be handled using __________.
- A. Preventive Maintenance
- B. Breakdown Maintenance
- C. Project-Oriented Maintenance
- D. Corrective Maintenance
Answer: C
NEW QUESTION 32
Which of the following is true about SAP Asset Intelligence Network cloud application? (Choose two.)
- A. It is the target of the application, to improve the visibility of machines
- B. A constructing engineer is the typical user of this application
- C. It is the target of the application to maintain a global directory of pieces of equipment, that uses general definitions
- D. A remote service technician is a typical user of this application
Answer: B,C
NEW QUESTION 33
Which of the following are valid scheduling parameters in the multiple-counter plan?
There are 2 correct answers to this question.
Response:
- A. OR-Link
- B. Call Horizon
- C. Scheduling Period
- D. Start Counter Reading
Answer: A,C
NEW QUESTION 34
To which SAP objects can the planner assign a maintenance order to make a budget available for this order?
There are 2 correct answers to this question.
Response:
- A. WBS element with allocated budget
- B. Functional location with allocated budget
- C. Investment program item with allocated budget
- D. Network header with allocated budget
Answer: A,D
NEW QUESTION 35
What is calculated from the sum of the stock values and the stock quantities of the individual partial stocks?
- A. Both policy-based and route-based VPN
- B. Policy-based VPN only
- C. Route-based VPN only
- D. Value of the overall stock
Answer: D
NEW QUESTION 36
What is external procurement in SAP S/4HANA assets management? (Choose three.)
- A. Account Assignment Element
- B. Perform strategic management of vendor relationships
- C. Procure external services
- D. Procure external materials
Answer: B,C,D
NEW QUESTION 37
Which object combination influences the display of fleet-specific tab strips and fields?
Please choose the correct answer.
Response:
- A. Equipment category and Fleet Object Type
- B. Fleet Object Type and vehicle usage indicator
- C. Equipment category and measuring point category
- D. Fleet Object Type and measuring point category
Answer: A
NEW QUESTION 38
What are created and assigned manually or automatically to the WBS elements or network activities?
- A. Quick mode
- B. Main mode
- C. Maintenance orders
- D. Aggressive mode
Answer: C
NEW QUESTION 39
The planner uses control key PM02 to purchase external services. What are valid process steps?
There are 3 correct answers to this question.
Response:
- A. Book the goods receipt.
- B. Create the purchase order.
- C. Accept the service entry sheet.
- D. Book the invoice.
- E. Create the service entry sheet.
Answer: B,C,E
NEW QUESTION 40
At which level can the planner estimate costs in a maintenance order?
Please choose the correct answer.
Response:
- A. At the value category level
- B. At the cost center level
- C. At the work center level
- D. At the component level
Answer: A
NEW QUESTION 41
Which of the following process features are part of breakdown maintenance?
There are 3 correct answers to this question.
Response:
- A. Orders created without notifications can be used within the Maintenance Event Builder
- B. Orders and notifications can be utilized in combination.
- C. Maintenance orders always need planning of maintenance tasks.
- D. Maintenance orders can be created as immediate orders without any planning.
- E. Notifications are used for documentation of technical findings and activities performed.
Answer: B,D,E
NEW QUESTION 42
You create an Equipment Task List for a piece of equipment without BOM assignment. How can you assign components to a Task List Operation of this Equipment Task List?
Please choose the correct answer.
Response:
- A. Assign the header material of a mater al BOM to the Equipment Task List Header.
Select components from the BOM to the Task List Operation. - B. Manually assign the BOM usage to a Task List Header.
Add components from the BOM to the Task List Operation. - C. Assign the header material of a material BOM as assembly to a Task List Operation.
Select components from the BOM to the Task List Operation. - D. Assign the BOM usage for free material assignment in Customizing.
Freely assign material as components to the Task List Operation.
Answer: D
NEW QUESTION 43
What is therefore given the value of the purchase price?
- A. The service
- B. Forward Traffic log
- C. Security log
- D. Event log
Answer: A
NEW QUESTION 44
To which objects can you assign a budget?
There are 2 correct answers to this question.
Response:
- A. Maintenance order
- B. WBS element
- C. Function allocation
- D. Planning plant
Answer: A,B
NEW QUESTION 45
Which object is mandatory within a refurbishment order?
Please choose the correct answer.
Response:
- A. Serial number
- B. Material
- C. Functional location
- D. Equipment
Answer: B
NEW QUESTION 46
What is often only implemented after other components, such as Financial Accounting (FI), Controlling (CO), or Materials Management (MM) have been implemented?
- A. Plant Maintenance
- B. Purchase Req for Dependent Requirements
- C. Reservation for Dependent Items
- D. Planned Order
Answer: A
NEW QUESTION 47
What is not to create a BOM for each technical object, but to create just one BOM, and then assign this to the relevant technical objects?
This avoids the use of redundant BOMs.
- A. View
- B. Session
- C. Request
- D. The aim
Answer: D
NEW QUESTION 48
Which of the following is true about SAP Work Manager? (Choose three.)
- A. It can be used with SAP S/4HAN
- B. It can be used with SAP ERP
- C. It is available in On Premise Edition and Cloud Edition
- D. It is available only on SAP Cloud Platform
Answer: A,B,C
NEW QUESTION 49
Which order type do you need when you refurbish defective parts?
Please choose the correct answer.
Response:
- A. Order type with refurbishment indicator
- B. Order type for breakdown maintenance
- C. Order type with investment indicator
- D. Order type for preventive maintenance
Answer: A
NEW QUESTION 50
......