NEW QUESTION 22
How should product-based planning be used as part of PRINCE2 Agile?

  • A. To enable team planning to be predictive
  • B. To track progress against the team plan
  • C. To plan by focusing on the features required
  • D. To create the project plan using empiricism

Answer: C

 

NEW QUESTION 23
According to PRINCE2 Agile, which form of communication shows that a team is vibrant and interactive?

  • A. Using social media to reach more people
  • B. Using visualization to display information
  • C. Using email to document discussions
  • D. Using meeting minutes to share decisions

Answer: B

 

NEW QUESTION 24
What is the definition of a timebox?

  • A. A period where work is carried out to achieve a goal
  • B. A regular event that looks at how processes can be improved
  • C. A tool to write a requirement in the form of who, what and why
  • D. A description of the rate of progress a team is making

Answer: A

 

NEW QUESTION 25
Which statement explains the setting of the cost tolerance for a project in an agile context?

  • A. Cost tolerance is fixed
  • B. Cost tolerance is flexed
  • C. Cost tolerance can be fixed or flexed
  • D. Cost tolerance can be fixed and flexed

Answer: B

 

NEW QUESTION 26
Which two statements are key responsibilities of supplier representative?
1. They highlight areas that the project may impact from a technical perspective.
2. They are partially assigned to the delivery team.
3. They create the project's specialist products.
4. They prioritize requirements.

  • A. 2 and 3
  • B. 1 and 2
  • C. 1 and 4
  • D. 3 and 4

Answer: C

 

NEW QUESTION 27
In which area is Agile strongest when blending with PRINCE2?

  • A. Project management
  • B. Product delivery
  • C. Product management
  • D. Project direction

Answer: B

 

NEW QUESTION 28
What is an epic?

  • A. A low-level requirement
  • B. A fine-grained user story
  • C. A detailed feature
  • D. A high-level requirement

Answer: D

 

NEW QUESTION 29
Which process can take place during a release review workshop?

  • A. Managing a stage boundary
  • B. Managing product delivery
  • C. Directing a project
  • D. Controlling a stage

Answer: B

 

NEW QUESTION 30
Which statement about the 'directing a project' process is CORRECT?

  • A. The project board should make decisions based on the Agilometer risks
  • B. A project board member should fulfill the product owner role within a delivery team
  • C. The project board should attend regular project progress meetings
  • D. The project board should increase the stage-level time tolerance

Answer: B

 

NEW QUESTION 31
Which statement about the 'embrace change' target is CORRECT?

  • A. It encourages the customer to raise new ideas
  • B. It reduces testing in order to meet deadlines
  • C. It reduces the planning of dependencies between projects
  • D. It minimizes the time needed to train a new team member

Answer: A

 

NEW QUESTION 32
Which is a typical characteristic of 'business as usual' work?

  • A. It is executed by program management
  • B. It is delivered by a temporary team
  • C. It requires a specific dedicated project manager
  • D. It is delivered by an established team

Answer: D

 

NEW QUESTION 33
Which is typically used in agile when estimating detailed requirements during sprint planning?

  • A. Rationalism
  • B. Visioning
  • C. Trading
  • D. T-shirt sizing

Answer: A

 

NEW QUESTION 34
How does the change theme regard change in PRINCE2 Agile?

  • A. As something to be avoided
  • B. As inevitable
  • C. As a necessity
  • D. As disruptive

Answer: B

 

NEW QUESTION 35
How is the 'tailor to suit the project' principle applied in an agile context?

  • A. By using the Agilometer to assess the project environment
  • B. By flexing what is produced to stay in control and deliver value
  • C. By fitting releases into planned management stages
  • D. By emphasizing tolerances on what is being delivered

Answer: B

 

NEW QUESTION 36
Which TWO are the purposes of a highlight report?
1. To describe the MoSCoW priority of user stories.
2. To summarize the status of a work package.
3. To summarize the stage status.
4. To report any potential issues and risks

  • A. 3 and 4
  • B. 2 and 3
  • C. 1 and 4
  • D. 1 and 2

Answer: A

Explanation:
Reference:
%20by%20them.&text=The%20project%20manager%20also%20uses,the%20project%20board%20could%20help

 

NEW QUESTION 37
Which statement explains the PRINCE2 Agile behavior of 'exploration'?

  • A. It empowers the project management team at the delivery level
  • B. It seeks out feedback collaboratively from project stakeholders
  • C. It uses the most effective channel to communicate information
  • D. It displays the progress rate to everyone using burn-down charts

Answer: B

 

NEW QUESTION 38
......