NEW QUESTION 22
How should product-based planning be used as part of PRINCE2 Agile?
- A. To enable team planning to be predictive
- B. To track progress against the team plan
- C. To plan by focusing on the features required
- D. To create the project plan using empiricism
Answer: C
NEW QUESTION 23
According to PRINCE2 Agile, which form of communication shows that a team is vibrant and interactive?
- A. Using social media to reach more people
- B. Using visualization to display information
- C. Using email to document discussions
- D. Using meeting minutes to share decisions
Answer: B
NEW QUESTION 24
What is the definition of a timebox?
- A. A period where work is carried out to achieve a goal
- B. A regular event that looks at how processes can be improved
- C. A tool to write a requirement in the form of who, what and why
- D. A description of the rate of progress a team is making
Answer: A
NEW QUESTION 25
Which statement explains the setting of the cost tolerance for a project in an agile context?
- A. Cost tolerance is fixed
- B. Cost tolerance is flexed
- C. Cost tolerance can be fixed or flexed
- D. Cost tolerance can be fixed and flexed
Answer: B
NEW QUESTION 26
Which two statements are key responsibilities of supplier representative?
1. They highlight areas that the project may impact from a technical perspective.
2. They are partially assigned to the delivery team.
3. They create the project's specialist products.
4. They prioritize requirements.
- A. 2 and 3
- B. 1 and 2
- C. 1 and 4
- D. 3 and 4
Answer: C
NEW QUESTION 27
In which area is Agile strongest when blending with PRINCE2?
- A. Project management
- B. Product delivery
- C. Product management
- D. Project direction
Answer: B
NEW QUESTION 28
What is an epic?
- A. A low-level requirement
- B. A fine-grained user story
- C. A detailed feature
- D. A high-level requirement
Answer: D
NEW QUESTION 29
Which process can take place during a release review workshop?
- A. Managing a stage boundary
- B. Managing product delivery
- C. Directing a project
- D. Controlling a stage
Answer: B
NEW QUESTION 30
Which statement about the 'directing a project' process is CORRECT?
- A. The project board should make decisions based on the Agilometer risks
- B. A project board member should fulfill the product owner role within a delivery team
- C. The project board should attend regular project progress meetings
- D. The project board should increase the stage-level time tolerance
Answer: B
NEW QUESTION 31
Which statement about the 'embrace change' target is CORRECT?
- A. It encourages the customer to raise new ideas
- B. It reduces testing in order to meet deadlines
- C. It reduces the planning of dependencies between projects
- D. It minimizes the time needed to train a new team member
Answer: A
NEW QUESTION 32
Which is a typical characteristic of 'business as usual' work?
- A. It is executed by program management
- B. It is delivered by a temporary team
- C. It requires a specific dedicated project manager
- D. It is delivered by an established team
Answer: D
NEW QUESTION 33
Which is typically used in agile when estimating detailed requirements during sprint planning?
- A. Rationalism
- B. Visioning
- C. Trading
- D. T-shirt sizing
Answer: A
NEW QUESTION 34
How does the change theme regard change in PRINCE2 Agile?
- A. As something to be avoided
- B. As inevitable
- C. As a necessity
- D. As disruptive
Answer: B
NEW QUESTION 35
How is the 'tailor to suit the project' principle applied in an agile context?
- A. By using the Agilometer to assess the project environment
- B. By flexing what is produced to stay in control and deliver value
- C. By fitting releases into planned management stages
- D. By emphasizing tolerances on what is being delivered
Answer: B
NEW QUESTION 36
Which TWO are the purposes of a highlight report?
1. To describe the MoSCoW priority of user stories.
2. To summarize the status of a work package.
3. To summarize the stage status.
4. To report any potential issues and risks
- A. 3 and 4
- B. 2 and 3
- C. 1 and 4
- D. 1 and 2
Answer: A
Explanation:
Reference:
%20by%20them.&text=The%20project%20manager%20also%20uses,the%20project%20board%20could%20help
NEW QUESTION 37
Which statement explains the PRINCE2 Agile behavior of 'exploration'?
- A. It empowers the project management team at the delivery level
- B. It seeks out feedback collaboratively from project stakeholders
- C. It uses the most effective channel to communicate information
- D. It displays the progress rate to everyone using burn-down charts
Answer: B
NEW QUESTION 38
......