SAP C-TS412-1909 Test Engine Dumps Training With 82 Questions
C-TS412-1909 Questions Pass on Your First Attempt Dumps for SAP Certified Application Associate Certified
SAP C-TS412-1909 Certification Exam Topics:
| Topic Areas | Topic Details, Courses, Books |
|---|---|
| Project Structures > 12% | Name the components of Work Breakdown Structure, Network and activities, Milestones |
| Cost and Budgets > 12% | Describe procedures for establishing budgets and reporting costs. |
| Material > 12% | Explain Work breakdown structure BOM, BOM PS Interface, component assignment in the network, material procurement |
| Reporting < 8% | Determine general reporting requirements and reporting requirements for cost centers. Configure cost center reporting and create report painter reports |
| Resources > 12% | Describe how the Resource Planning process integrates with HCM |
| Dates > 12% | Describe the importance of various dates which can be tracked for projects |
| Revenues and Payments > 12% | Describe the characteristics of Revenues & Payments. |
NEW QUESTION 45
You want to use billing for a customer project. Which customizing object controls the billing of sales order items?
- A. Schedule line category
- B. Item category
- C. Requirements type
- D. Requirements class
Answer: B
NEW QUESTION 46
Which statements describe planned and actual revenue for WBS elements? Note: There are 2 correct Answers to this question.
- A. Planned revenue can be transferred from a sales quotation.
- B. Planned revenue requires a sales order assigned to a WBS element.
- C. Actual revenue is posted via a billing plan assigned to a WBS element.
- D. Actual revenue is posted via a billing document created from a sales order
Answer: A,D
NEW QUESTION 47
You are using WBS elements and activities are NOT assigned. Which statements apply to the maintenance of the actual start and finish? Note: There are 2 correct Answers to this question.
- A. You can always maintain the actual start and finish date of a WBS element.
- B. You can only maintain the actual start of a WBS element if the finish date is not maintained.
- C. You can always maintain the actual start if the WBS element has the status "Released" or "Partially released".
- D. You can only maintain the actual finish if all lower-level WBS elements have an actual finish date and the status of the WBS element is "Released".
Answer: C,D
NEW QUESTION 48
In your project, you work with a network and external activities. You have created a purchase requisition. The corresponding purchase order is created as well. Now, you increase the quantity of the external activity. How does the system support this scenario?
- A. A workflow can be triggered to inform the purchasing group.
- B. The system automatically creates a new purchase requisition with the difference to the original quantity.
- C. The purchase order can be updated in Goods Receipt for Purchase Order (MIGO).
- D. The purchase order is updated automatically to match the new quantity while saving the project.
Answer: A
NEW QUESTION 49
Which objects do you have to maintain to enable automatic assignment of material components to the project? Note: There are 2 correct Answers to this question.
- A. Network activity
- B. BOM item
- C. WBS element
- D. Material master
Answer: A,B
NEW QUESTION 50
You used reductions to reduce the scheduled duration of all internally-processed activities in your project. However, the duration did not changed after overall network scheduling.
What do you check? Note: There are 2 correct Answers to this question.
- A. If the reduction strategy is set in the network header
- B. If the appropriate reduction type is set in the parameters for network scheduling
- C. If the maximum reduction level is less than 100
- D. If the reduction strategy is set in each activity
Answer: A,B
NEW QUESTION 51
How can you update the degree of processing for an activity?
- A. By scheduling the activity
- B. By changing the activity
- C. By confirming the activity
- D. By using results analysis
Answer: C
NEW QUESTION 52
Float time is calculated during scheduling. Which of the following statements about float time are correct? Note: There are 3 correct Answers to this question.
- A. By default, critical activities have a float time, which is less than or equal to zero.
- B. The float time of WBS elements is calculated by extrapolation.
- C. The maximum size of a free float is as large as the total float of an activity.
- D. Activities with the time constraint "Must start on" always have a negative float time.
- E. Float time can be negative.
Answer: A,D,E
NEW QUESTION 53
You have created an internally-processed network activity, and assigned a work center and the work.
After saving, you discover that no planned costs are displayed in the cost element report for the activity.
What could be the reason? Note: There are 3 correct Answers to this question.
- A. The activity output price for the activity type and cost center assigned to the work center is not maintained.
- B. The duration is missing in the activity.
- C. The formula for costing in the work center is incorrect.
- D. The Determine Costs indicator in the network header rules out planned cost calculation.
- E. Integrated planning for the network is active.
Answer: A,B,D
NEW QUESTION 54
You want to assign milestones to WBS elements. For what can you use these milestones? Note: There are 2 correct Answers to this question.
- A. To start workflow tasks
- B. To set an actual finish date for WBS elements
- C. For trend analysis
- D. To transfer the actual date to the billing plan
Answer: C,D
NEW QUESTION 55
An external component is assigned to a network activity. The delivery date for the purchase requisition depends on the dates of the network activity. What controls whether the delivery date is defined by the earliest or latest scheduled dates?
- A. The table of MRP controllers
- B. The control key
- C. The network profile
- D. The scheduling parameters for the network
Answer: D
NEW QUESTION 56
What is the reason for assigning billing plans in customer projects?
- A. Billing plans enable the billing process to be carried out.
- B. Billing plans are prerequisites for quotation creation.
- C. Billing plans are used for revenue planning.
- D. Billing plans are copied automatically to the sales order item.
Answer: A
NEW QUESTION 57
For which objects can billing plans be created? Note: There are 2 correct Answers to this question.
- A. Milestones
- B. Project definition
- C. Sales order items
- D. WBS elements
Answer: C,D
NEW QUESTION 58
What are the prerequisites for resource-related billing? Note: There are 2 correct Answers to this question.
- A. A dynamic item processor (DIP) profile with the appropriate settings
- B. Released WBS elements, activities, and/or activity elements
- C. An activity-account-assigned network that is assigned to a sales order item
- D. A header-account-assigned network that is assigned to a sales order item
Answer: A,B
NEW QUESTION 59
How can you search in the structure overview based on the user status? Note: There are 2 correct Answers to this question.
- A. By searching for the individual status
- B. By searching via status selection profile
- C. By searching via status combination code
- D. By searching for the status profile
Answer: A,D
NEW QUESTION 60
Which orders or documents can be displayed in Project-Oriented Procurement (ProMan)? Note: There are 2 correct Answers to this question.
- A. Sales order items
- B. Reservations
- C. Internal orders
- D. Purchase order items
Answer: B,D
NEW QUESTION 61
You have assigned a budget to WBS elements within your project. What function can be used to check assigned values against the current budget?
- A. Cost forecast
- B. Results analysis
- C. Easy Cost Planning
- D. Availability control
Answer: D
NEW QUESTION 62
Which of the following statements apply to project versions? Note: There are 2 correct Answers to this question.
- A. Project versions are mandatory for Milestone Trend Analysis (MTA).
- B. Project versions can be changed.
- C. Project versions can be created automatically based on user status.
- D. Manually created project versions always require a project version profile.
Answer: A,B
NEW QUESTION 63
......
C-TS412-1909 Exam Certification Details:
| Cut Score: | 51% |
| Sample Questions: | SAP C-TS412-1909 Exam Sample Question |
| Exam: | 80 questions |
| Level: | Associate |
| Languages: | English |
C-TS412-1909 Practice Test Pdf Exam Material: https://www.testpdf.com/C-TS412-1909-exam-braindumps.html
C-TS412-1909 Answers C-TS412-1909 Free Demo Are Based On The Real Exam: https://drive.google.com/open?id=17L1csYheXxWrFEl0GLNIDrhr6tHI4T4s